TX10 Hummingbird Storage πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-07
Construction start 2023-09
Operation start
Estimated start 2024-08
Construction time
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Key Capture Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.33884809055068+-95.11487066910252
Coordinates
33.33884809055068, -95.11487066910252
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
718 / 65693

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-07 report):

Plant Name / State
TX10 Hummingbird Storage / TX
go live / power
2024-08 / 100MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
65693 / TX10
Entity name / entity id
Key Capture Energy / 63289
Changes:
2024-06
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2024-07 -> 2024-08 delayed by 1 month
2024-04
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2024-08 -> 2024-07 accelerated by 1 month
2024-03
date: 2024-07 -> 2024-08 delayed by 1 month
2023-12
date: 2024-04 -> 2024-07 delayed by 3 months
2023-09
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-07
date: 2024-03 -> 2024-04 delayed by 1 month
2023-03
date: 2024-01 -> 2024-03 delayed by 2 months
2023-01
date: 2023-08 -> 2024-01 delayed by 5 months