Aratina Solar Center 1 Hybrid πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2020-09
Construction start
Operation start
Estimated start 2025-11
Construction time
Capacity in MWh
250
πŸ“ This is an estimate
Maximum Power in MW
125
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ 91MC 8me LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.93693686027558+-121.04439962977752
Coordinates
40.93693686027558, -121.04439962977752
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
178 / 61167

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2020-09 report):

Plant Name / State
Aratina Solar Center 1 Hybrid / CA
go live / power
2025-11 / 125MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
61167 / BESS
Entity name / entity id
91MC 8me LLC / 60796
Changes:
2024-03
date: 2025-06 -> 2025-11 delayed by 5 months
mw: 50 -> 125
2023-05
date: 2023-12 -> 2025-06 delayed by 18 months
2022-11
date: 2023-09 -> 2023-12 delayed by 3 months
2021-10
date: 2022-08 -> 2023-09 delayed by 13 months