Azure Sky Wind Project, LLC Hybrid πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2020-12
Construction start
Operation start 2024-04
Estimated start 2022-03
Construction time
Capacity in MWh
240
πŸ“ This is an estimate
Maximum Power in MW
120
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Azure Sky Wind Project, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.526939371284264+-95.1731198926975
Coordinates
33.526939371284264, -95.1731198926975
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
242 / 64164

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2020-12 report):

Plant Name / State
Azure Sky Wind Project, LLC Hybrid / TX
go live / power
2024-04 / 120MW
status / status verbose
operation / operation
Plant id / generator id
64164 / ASWBE
Entity name / entity id
Azure Sky Wind Project, LLC / 63784
Changes:
2024-06
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
date: 2024-05 -> 2024-04 accelerated by 1 month
2024-05
date: 2024-03 -> 2024-05 delayed by 2 months
2024-04
date: 2024-02 -> 2024-03 delayed by 1 month
2024-03
date: 2024-01 -> 2024-02 delayed by 1 month
2024-02
date: 2023-12 -> 2024-01 delayed by 1 month
2023-12
date: 2023-10 -> 2023-12 delayed by 2 months
2023-11
date: 2023-09 -> 2023-10 delayed by 1 month
2023-10
date: 2023-08 -> 2023-09 delayed by 1 month
2023-08
date: 2023-06 -> 2023-08 delayed by 2 months
2023-06
date: 2023-04 -> 2023-06 delayed by 2 months
2023-05
date: 2023-03 -> 2023-04 delayed by 1 month
2023-03
date: 2023-01 -> 2023-03 delayed by 2 months
2023-01
date: 2022-12 -> 2023-01 delayed by 1 month
2022-12
date: 2022-11 -> 2022-12 delayed by 1 month
2022-10
date: 2022-09 -> 2022-11 delayed by 2 months
2022-07
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2022-05
date: 2022-03 -> 2022-09 delayed by 6 months
2022-03
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete