Harryoung PV and BESS πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2024-08 |
Construction start |
|
Operation start |
|
Estimated start |
2027-05 |
Construction time |
|
Capacity in MWh
380
π This is an estimate
Maximum Power in MW
190
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Gransolar Texas Four LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.39163256713626+-95.46555141629162
Coordinates
33.39163256713626, -95.46555141629162
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1591 / 67777
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-01
report (Project first appeared in the
2024-08
report):
Plant Name / State
Harryoung PV and BESS / TX
go live / power
2027-05 / 190MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
67777 / GRS4B
Entity name / entity id
Gransolar Texas Four LLC / 66374