Proxima πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-03
Construction start 2023-06
Operation start 2024-04
Estimated start 2023-10
Construction time 10 months -> 32 MWh/m
Capacity in MWh
324
πŸ“ This is an estimate
Maximum Power in MW
162
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Proxima Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.03803592366989+-121.41654744719
Coordinates
41.03803592366989, -121.41654744719
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
952 / 66270

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-03 report):

Plant Name / State
Proxima / CA
go live / power
2024-04 / 162MW
status / status verbose
operation / operation
Plant id / generator id
66270 / PRXBS
Entity name / entity id
Proxima Solar, LLC / 65394
Changes:
2024-06
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2024-04
date: 2024-02 -> 2024-04 delayed by 2 months
2024-03
date: 2024-01 -> 2024-02 delayed by 1 month
2024-01
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2023-10
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-08
date: 2023-10 -> 2024-01 delayed by 3 months
2023-06
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-05
date: 2023-09 -> 2023-10 delayed by 1 month