IP Radian, LLC ππ€
Status
construction
Country / State / Closest City
πΊπΈ usa / texas / brown county
Dates
First heard |
2024-07 |
Construction start |
|
Operation start |
|
Estimated start |
2025-03 |
Construction time |
|
Capacity in MWh
320
Maximum Power in MW
160
Manufacturer
tesla
Type / Number of Packs / Cells
megapack / 86 /
Customer / Owner / Developer
/ IP Radian, LLC / Intersect Power
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:31.5481+-99.1872
Coordinates
31.5481, -99.1872
β
The site is known, coords are +/- 1 kilometer
Notes
coords from the gem website
it says 86 megepacks per project in power progress article, and 320MWh 2 hour system
todo: need to find eia project for it
Project website
Sources
https://www.gem.wiki/Radian_solar_farm
https://www.intersectpower.com/press-releases/tesla-provides-intersect-power-with-15-3-gwh-of-megapacks-for-solar-storage-projects/
https://www.powerprogress.com/news/tesla-supplies-bess-megapacks-to-intersect-power/8038321.article
Internal / External id
1477 / 64859
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2025-04
report (Project first appeared in the
2024-07
report):
Plant Name / State
IP Radian, LLC / TX
go live / power
2025-03 / 160MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
64859 / RADBA
Entity name / entity id
IP Radian, LLC / 64370
Changes:
2024-12
date: 2025-02 -> 2025-03 delayed by
1 month
2024-11
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2024-08
status_verbose: (V) Under construction, more than 50 percent complete -> (U) Under construction, less than or equal to 50 percent complete
date: 2024-12 -> 2025-02 delayed by
2 months