Cameron Wind 1 LLC πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2021-11 |
Construction start |
2023-05 |
Operation start |
2024-03 |
Estimated start |
2022-10 |
Construction time |
10 months -> 3 MWh/m
|
Capacity in MWh
32
π This is an estimate
Maximum Power in MW
16
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Cameron Wind 1 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.60453116095374+-95.1641099430736
Coordinates
33.60453116095374, -95.1641099430736
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
563 / 59118
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2021-11
report):
Plant Name / State
Cameron Wind 1 LLC / TX
go live / power
2024-03 / 16MW
status / status verbose
operation / operation
Plant id / generator id
59118 / SABAL
Entity name / entity id
Cameron Wind 1 LLC / 58939
Changes:
2024-05
status: construction -> operation πΎ π πΈ
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
2024-04
date: 2024-02 -> 2024-03 delayed by
1 month
mw: 24 -> 16
2024-03
date: 2024-01 -> 2024-02 delayed by
1 month
2024-02
date: 2023-12 -> 2024-01 delayed by
1 month
2023-12
date: 2023-11 -> 2023-12 delayed by
1 month
2023-11
date: 2023-10 -> 2023-11 delayed by
1 month
2023-10
date: 2023-09 -> 2023-10 delayed by
1 month
2023-09
date: 2023-08 -> 2023-09 delayed by
1 month
2023-05
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-03
date: 2023-06 -> 2023-08 delayed by
2 months
2022-10
status: construction -> planning
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (T) Regulatory approvals received. Not under construction
date: 2022-10 -> 2023-06 delayed by
8 months
2022-08
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete