Cameron Wind 1 LLC πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2021-11
Construction start 2023-05
Operation start
Estimated start 2024-01
Construction time
Capacity in MWh
48
πŸ“ This is an estimate
Maximum Power in MW
24
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Cameron Wind 1 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.60453116095374+-95.1641099430736
Coordinates
33.60453116095374, -95.1641099430736
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
563 / 59118

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-11 report):

Plant Name / State
Cameron Wind 1 LLC / TX
go live / power
2024-01 / 24MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
59118 / SABAL
Entity name / entity id
Cameron Wind 1 LLC / 58939
Changes:
2024-02
date: 2023-12 -> 2024-01 delayed by 1 month
2023-12
date: 2023-11 -> 2023-12 delayed by 1 month
2023-11
date: 2023-10 -> 2023-11 delayed by 1 month
2023-10
date: 2023-09 -> 2023-10 delayed by 1 month
2023-09
date: 2023-08 -> 2023-09 delayed by 1 month
2023-05
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-03
date: 2023-06 -> 2023-08 delayed by 2 months
2022-10
status: construction -> planning
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (T) Regulatory approvals received. Not under construction
date: 2022-10 -> 2023-06 delayed by 8 months
2022-08
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete