Papago Energy Storage β‘οΈππ€ 
Status 
operation 
Country / State / Closest CityπΊπΈ usa / arizona / Maricopa County
Dates
    
        
            
                | First heard | 2024-06 | 
            
                | Construction start | 2024-07 | 
            
                | Operation start | 2025-05 | 
            
                | Estimated start |  | 
            
            
                | Construction time | 10 months -> 120 MWh/m | 
        
     
 
Capacity in MWh 
    1200
    
Maximum Power in MW300
Manufacturer 
Type / Number of Packs / Cells /  / 
Customer / Owner / DeveloperRecurrent Energy / RE Papago LLC /  
Use case300MW solar farm support
Link to google maps satellite viewhttp://maps.google.com/maps?z=19&t=k&q=loc:33.481046+-113.03863 
Coordinates
    33.481046, -113.03863 
    
 β
 Coords are exact (+/- 50m)
Notes
    
     
     
Project websitehttps://recurrentenergy.com/project/papago/  
Sources
    
    https://www.maricopa.gov/AgendaCenter/ViewFile/Item/7254?fileID=56298  
     
Internal / External id
    75 / 66779
 U.S. EIA data 
The government data source for this battery is the U.S. Energy Information Administration (EIA)
    https://www.eia.gov/electricity/monthly/
Info from the 
2025-09 report (Project first appeared in the 
2024-06 report):
Plant Name / State
Papago Energy Storage / AZ
go live / power2025-05 / 300MW
status / status verboseoperation / operation 
Plant id / generator id66779 / PPABA
Entity name / entity idRE Papago LLC / 65751
Changes:
    2025-07
    
        status: construction -> operation πΎ π πΈ
    
        status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation 
     
    
2025-05
    
        status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation 
     
    
2024-11
    
        status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete 
     
    
2024-07
    
        status: planning -> construction ποΈ
    
        status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete