AES ES Alamitos 2 LLC πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2024-06
Construction start
Operation start 2024-11
Estimated start 2024-09
Construction time
Capacity in MWh
164
πŸ“ This is an estimate
Maximum Power in MW
82
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.94954736320376+-121.17426295600941
Coordinates
40.94954736320376, -121.17426295600941
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1337 / 67579

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2024-06 report):

Plant Name / State
AES ES Alamitos 2 LLC / CA
go live / power
2024-11 / 82MW
status / status verbose
operation / operation
Plant id / generator id
67579 / ALMT2
Entity name / entity id
AES Clean Energy / 64904
Changes:
2025-01
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2024-10
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2024-09
date: 2024-09 -> 2024-11 delayed by 2 months