Quest Solar πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / south carolina /
Dates
First heard |
2024-04 |
Construction start |
|
Operation start |
|
Estimated start |
2026-06 |
Construction time |
|
Capacity in MWh
100
π This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Quest Solar /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:34.39676+-79.792266
Coordinates
34.39676, -79.792266
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1355 / 62299
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-04
report):
Plant Name / State
Quest Solar / SC
go live / power
2026-06 / 50MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
62299 / 67
Entity name / entity id
Quest Solar / 61807
Changes: