Alamo 7 BESS 2 πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-03 |
Construction start |
|
Operation start |
|
Estimated start |
2025-12 |
Construction time |
|
Capacity in MWh
300
π This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Consolidated Edison Development Inc. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.73176250275819+-95.36367096235749
Coordinates
33.73176250275819, -95.36367096235749
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
986 / 66298
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-03
report):
Plant Name / State
Alamo 7 BESS 2 / TX
go live / power
2025-12 / 150MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66298 / A7BS2
Entity name / entity id
Consolidated Edison Development Inc. / 56769
Changes:
2024-06
date: 2024-12 -> 2025-12 delayed by
12 months
2024-02
date: 2024-05 -> 2024-12 delayed by
7 months