Clear Fork Creek Solar and BESS SLF πŸ“β€οΈπŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-09
Construction start
Operation start
Estimated start 2025-12
Construction time
Capacity in MWh
1200
πŸ“ This is an estimate
Maximum Power in MW
600
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Solar Proponent LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.689916016041195+-95.19680178539501
Coordinates
33.689916016041195, -95.19680178539501
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
784 / 65842

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-09 report):

Plant Name / State
Clear Fork Creek Solar and BESS SLF / TX
go live / power
2025-12 / 600MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
65842 / CFCBS
Entity name / entity id
Solar Proponent LLC / 65079
Changes:
2023-05
date: 2024-03 -> 2025-12 delayed by 21 months