Manatee Solar Energy Center πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / florida / Parrish / Manatee County
Dates
First heard 2020-09
Construction start 2021-01
Operation start 2021-11
Estimated start
Construction time 10 months -> 90 MWh/m
Capacity in MWh
900
Maximum Power in MW
409
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
Florida Power and Light (FPL) / Florida Power & Light Co /
Use case
solar farm support
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:27.598383+-82.349213
Coordinates
27.598383, -82.349213
βœ… Coords are exact (+/- 50m)
Notes
Already 75% complete in August 2021, 132 shipping containers
Project website
Sources
https://www.world-energy.org/article/19846.html
https://www.youtube.com/watch?v=ZYbvXAS9buQ
https://www.energy-storage.news/work-begins-on-409mw-900mwh-florida-battery-project-to-ease-natural-gas-plants-into-retirement/
Internal / External id
71 / 60014

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Manatee Solar Energy Center / FL
go live / power
2021-11 / 409MW
status / status verbose
operation / operation
Plant id / generator id
60014 / BMS
Entity name / entity id
Florida Power & Light Co / 6452
Changes:
2022-01
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2021-08
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2021-01
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete