Hop Hill Solar Generation and BESS πŸ“β€οΈπŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / washington /
Dates
First heard 2025-01
Construction start
Operation start
Estimated start 2028-12
Construction time
Capacity in MWh
2800
πŸ“ This is an estimate
Maximum Power in MW
1400
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ HOHI bn, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:48.368592513578186+-118.17975612696499
Coordinates
48.368592513578186, -118.17975612696499
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1672 / 68342

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2025-01 report):

Plant Name / State
Hop Hill Solar Generation and BESS / WA
go live / power
2028-12 / 1400MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
68342 / HOHI2
Entity name / entity id
HOHI bn, LLC / 66737
Changes: