McFarland A Solar and Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2023-06
Construction start 2023-09
Operation start 2023-12
Estimated start 2023-12
Construction time 3 months -> 66 MWh/m
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.53961436488624+-110.07356319022644
Coordinates
36.53961436488624, -110.07356319022644
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1009 / 66636

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-06 report):

Plant Name / State
McFarland A Solar and Storage / AZ
go live / power
2023-12 / 100MW
status / status verbose
operation / operation
Plant id / generator id
66636 / BESS
Entity name / entity id
AES Clean Energy / 64904
Changes:
2024-02
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2024-01
date: 2023-11 -> 2023-12 delayed by 1 month
2023-11
date: 2023-12 -> 2023-11 accelerated by 1 month
2023-09
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete