Azalea (CA) πππ
Status
planning
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2024-06 |
Construction start |
|
Operation start |
|
Estimated start |
2025-12 |
Construction time |
|
Capacity in MWh
120
π This is an estimate
Maximum Power in MW
60
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Idemitsu Renewables /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.98395968045898+-121.10912098932751
Coordinates
40.98395968045898, -121.10912098932751
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1338 / 66890
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-06
report):
Plant Name / State
Azalea (CA) / CA
go live / power
2025-12 / 60MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66890 / AZAL
Entity name / entity id
Idemitsu Renewables / 63137