Castor πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-09
Construction start 2024-03
Operation start
Estimated start 2024-12
Construction time
Capacity in MWh
400
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Engie North America /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.255035819383764+-95.41803317206394
Coordinates
33.255035819383764, -95.41803317206394
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
793 / 65870

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2022-09 report):

Plant Name / State
Castor / TX
go live / power
2024-12 / 200MW
status / status verbose
construction / (U) Under construction, less than or equal to 50 percent complete
Plant id / generator id
65870 / CASTR
Entity name / entity id
Engie North America / 56201
Changes:
2024-03
entity id: 63883 -> 56201
entity name: Broad Reach Power -> Engie North America
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-04
date: 2024-05 -> 2024-12 delayed by 7 months