Madero Grid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2020-09 |
Construction start |
2021-05 |
Operation start |
2023-03 |
Estimated start |
2022-04 |
Construction time |
22 months -> 9 MWh/m
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Madero Grid, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.61383149473758+-95.22152314494501
Coordinates
33.61383149473758, -95.22152314494501
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
244 / 63757
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Madero Grid / TX
go live / power
2023-03 / 100MW
status / status verbose
operation / operation
Plant id / generator id
63757 / MAD01
Entity name / entity id
Madero Grid, LLC / 63451
Changes:
2023-05
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-04
date: 2023-02 -> 2023-03 delayed by
1 month
2023-01
date: 2022-12 -> 2023-02 delayed by
2 months
2022-11
date: 2022-10 -> 2022-12 delayed by
2 months
2022-10
date: 2022-08 -> 2022-10 delayed by
2 months
2022-09
date: 2022-07 -> 2022-08 delayed by
1 month
2022-08
date: 2022-06 -> 2022-07 delayed by
1 month
2022-05
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-04
date: 2022-05 -> 2022-06 delayed by
1 month
2022-02
date: 2022-06 -> 2022-05 accelerated by
1 month
2022-01
date: 2022-04 -> 2022-06 delayed by
2 months
2021-10
date: 2022-01 -> 2022-04 delayed by
3 months
2021-05
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2021-03
date: 2021-12 -> 2022-01 delayed by
1 month
2021-01
mw: 200 -> 100
2020-11
date: 2021-09 -> 2021-12 delayed by
3 months
2020-10
date: 2021-07 -> 2021-09 delayed by
2 months