Henrietta D Energy Storage LLC πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2020-09
Construction start 2020-12
Operation start 2021-11
Estimated start
Construction time 11 months -> 1 MWh/m
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Convergent Energy and Power LP /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.82594736691591+-121.20363569775502
Coordinates
40.82594736691591, -121.20363569775502
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
196 / 60641

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Henrietta D Energy Storage LLC / CA
go live / power
2021-11 / 10MW
status / status verbose
operation / operation
Plant id / generator id
60641 / HDES1
Entity name / entity id
Convergent Energy and Power LP / 61978
Changes:
2022-01
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2021-12
date: 2021-10 -> 2021-11 delayed by 1 month
2021-11
date: 2021-09 -> 2021-10 delayed by 1 month
2021-07
date: 2021-06 -> 2021-09 delayed by 3 months
2021-02
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2021-04 -> 2021-06 delayed by 2 months
2021-01
date: 2021-03 -> 2021-04 delayed by 1 month
2020-12
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2020-10
date: 2021-01 -> 2021-03 delayed by 2 months