EDPR CA Solar Park VI LLC (CA) Hybrid πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2020-09
Construction start
Operation start
Estimated start 2024-12
Construction time
Capacity in MWh
80
πŸ“ This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ EDPR CA Solar Park VI LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.3585390160412+-121.22341278539501
Coordinates
41.3585390160412, -121.22341278539501
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
184 / 62892

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
EDPR CA Solar Park VI LLC (CA) Hybrid / CA
go live / power
2024-12 / 40MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
62892 / SONR2
Entity name / entity id
EDPR CA Solar Park VI LLC / 62760
Changes:
2023-02
date: 2023-12 -> 2024-12 delayed by 12 months
2022-04
date: 2022-12 -> 2023-12 delayed by 12 months