Desert Star Hybrid πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2021-04
Construction start 2022-03
Operation start 2023-02
Estimated start
Construction time 11 months -> 1 MWh/m
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Arizona Public Service Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.25778388821952+-109.81356205730502
Coordinates
36.25778388821952, -109.81356205730502
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
156 / 59444

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2021-04 report):

Plant Name / State
Desert Star Hybrid / AZ
go live / power
2023-02 / 10MW
status / status verbose
operation / operation
Plant id / generator id
59444 / DS10M
Entity name / entity id
Arizona Public Service Co / 803
Changes:
2023-04
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-02
date: 2022-12 -> 2023-02 delayed by 2 months
2022-08
date: 2022-06 -> 2022-12 delayed by 6 months
2022-03
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
2021-06
date: 2021-12 -> 2022-06 delayed by 6 months