Desert Harvest II LLC πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2020-12
Construction start 2021-01
Operation start 2021-01
Estimated start
Construction time
Capacity in MWh
70
πŸ“ This is an estimate
Maximum Power in MW
35
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Desert Harvest II LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.37670833623373+-121.48461356921983
Coordinates
41.37670833623373, -121.48461356921983
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
187 / 64103

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2022-02 report (Project first appeared in the 2020-12 report):

Plant Name / State
Desert Harvest II LLC / CA
go live / power
2021-01 / 35MW
status / status verbose
operation / operation
Plant id / generator id
64103 / DH003
Entity name / entity id
Desert Harvest II LLC / 63731
Changes:
2021-03
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
date: 2021-02 -> 2021-01 accelerated by 1 month
2021-02
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2020-12 -> 2021-02 delayed by 2 months
2021-01
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete