Lancaster Area Battery πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-11
Construction start
Operation start 2022-09
Estimated start
Construction time
Capacity in MWh
254
πŸ“ This is an estimate
Maximum Power in MW
127
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Distributed Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.912677+-121.300049
Coordinates
40.912677, -121.300049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
855 / 66050

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2022-11 report):

Plant Name / State
Lancaster Area Battery / CA
go live / power
2022-09 / 127MW
status / status verbose
operation / operation
Plant id / generator id
66050 / LAB
Entity name / entity id
AES Distributed Energy / 61012
Changes: