Hyder Solar Hybrid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / arizona /
Dates
First heard |
2020-09 |
Construction start |
2022-10 |
Operation start |
2023-04 |
Estimated start |
2022-12 |
Construction time |
6 months -> 5 MWh/m
|
Capacity in MWh
32
π This is an estimate
Maximum Power in MW
16
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Arizona Public Service Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.344132178933755+-109.98282635188055
Coordinates
36.344132178933755, -109.98282635188055
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
153 / 57563
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2020-09
report):
Plant Name / State
Hyder Solar Hybrid / AZ
go live / power
2023-04 / 16MW
status / status verbose
operation / operation
Plant id / generator id
57563 / H116M
Entity name / entity id
Arizona Public Service Co / 803
Changes:
2023-06
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-05
date: 2023-03 -> 2023-04 delayed by
1 month
2023-04
date: 2023-02 -> 2023-03 delayed by
1 month
2023-02
date: 2022-12 -> 2023-02 delayed by
2 months
2022-10
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete
2021-03
date: 2021-12 -> 2022-12 delayed by
12 months