Ignacio Grid Energy Storage System πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2020-11
Construction start 2021-06
Operation start 2023-03
Estimated start 2022-05
Construction time 21 months -> 9 MWh/m
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Ignacio Grid, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.64336397668374+-95.41097974903644
Coordinates
33.64336397668374, -95.41097974903644
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
247 / 64089

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2020-11 report):

Plant Name / State
Ignacio Grid Energy Storage System / TX
go live / power
2023-03 / 100MW
status / status verbose
operation / operation
Plant id / generator id
64089 / IGN01
Entity name / entity id
Ignacio Grid, LLC / 63723
Changes:
2023-05
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-04
date: 2023-02 -> 2023-03 delayed by 1 month
2023-01
date: 2022-12 -> 2023-02 delayed by 2 months
2022-11
date: 2022-10 -> 2022-12 delayed by 2 months
2022-10
date: 2022-08 -> 2022-10 delayed by 2 months
2022-09
date: 2022-07 -> 2022-08 delayed by 1 month
2022-08
date: 2022-06 -> 2022-07 delayed by 1 month
2022-05
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-01
date: 2022-05 -> 2022-06 delayed by 1 month
2021-10
date: 2022-03 -> 2022-05 delayed by 2 months
2021-06
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2021-05
status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
2021-03
date: 2022-01 -> 2022-03 delayed by 2 months
2021-01
date: 2021-06 -> 2022-01 delayed by 7 months