Fallbrook Energy Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2020-09
Construction start 2021-02
Operation start 2023-03
Estimated start
Construction time 25 months -> 3 MWh/m
Capacity in MWh
80
πŸ“ This is an estimate
Maximum Power in MW
40
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ San Diego Gas & Electric Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.30551484072874+-121.1672095329819
Coordinates
41.30551484072874, -121.1672095329819
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
183 / 61365

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2020-09 report):

Plant Name / State
Fallbrook Energy Storage / CA
go live / power
2023-03 / 40MW
status / status verbose
operation / operation
Plant id / generator id
61365 / FBES
Entity name / entity id
San Diego Gas & Electric Co / 16609
Changes:
2023-05
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2023-03
date: 2023-01 -> 2023-03 delayed by 2 months
2023-01
date: 2022-12 -> 2023-01 delayed by 1 month
2022-12
date: 2022-10 -> 2022-12 delayed by 2 months
2022-11
date: 2022-09 -> 2022-10 delayed by 1 month
2022-10
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2022-08 -> 2022-09 delayed by 1 month
2022-09
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2022-06
date: 2022-06 -> 2022-08 delayed by 2 months
2021-11
date: 2021-12 -> 2022-06 delayed by 6 months
2021-03
date: 2021-05 -> 2021-12 delayed by 7 months
2021-02
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete