Cunningham Storage πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-03
Construction start 2022-09
Operation start 2023-08
Estimated start
Construction time 11 months -> 34 MWh/m
Capacity in MWh
380
πŸ“ This is an estimate
Maximum Power in MW
190
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Acciona Energy USA Global, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.61100329690874+-95.38746833894474
Coordinates
33.61100329690874, -95.38746833894474
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
627 / 65410

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-03 report):

Plant Name / State
Cunningham Storage / TX
go live / power
2023-08 / 190MW
status / status verbose
operation / operation
Plant id / generator id
65410 / SPUT
Entity name / entity id
Acciona Energy USA Global, LLC / 57416
Changes:
2023-10
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-09
date: 2023-07 -> 2023-08 delayed by 1 month
2023-07
date: 2023-06 -> 2023-07 delayed by 1 month
2023-06
date: 2023-05 -> 2023-06 delayed by 1 month
2023-04
entity id: 64757 -> 57416
entity name: BT Cunningham Storage, LLC -> Acciona Energy USA Global, LLC
date: 2023-03 -> 2023-05 delayed by 2 months
2023-03
date: 2023-02 -> 2023-03 delayed by 1 month
2022-11
date: 2022-12 -> 2023-02 delayed by 2 months
2022-09
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (V) Under construction, more than 50 percent complete