Baldy Mesa 2_Silver Peak Hybrid πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-09
Construction start
Operation start
Estimated start 2024-06
Construction time
Capacity in MWh
50
πŸ“ This is an estimate
Maximum Power in MW
25
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.122677+-121.220049
Coordinates
41.122677, -121.220049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1040 / 66885

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-09 report):

Plant Name / State
Baldy Mesa 2_Silver Peak Hybrid / CA
go live / power
2024-06 / 25MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
66885 / SPKBS
Entity name / entity id
AES Clean Energy / 64904
Changes:
2023-11
date: 2023-12 -> 2024-06 delayed by 6 months