Westwing πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / arizona /
Dates
First heard 2024-09
Construction start
Operation start
Estimated start 2025-01
Construction time
Capacity in MWh
400
πŸ“ This is an estimate
Maximum Power in MW
200
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Clean Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.60016423408578+-109.84569982472001
Coordinates
36.60016423408578, -109.84569982472001
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1524 / 67855

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
This project has 2 generator ids under the same plant id
Info from the 2025-01 report (Project first appeared in the 2024-09 report):

Plant Name / State
Westwing / AZ
go live / power
2025-01 / 118MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
67855 / WEST2
Entity name / entity id
AES Clean Energy / 64904
Changes:
2025-01
date: 2024-12 -> 2025-01 delayed by 1 month
2024-12
date: 2024-11 -> 2024-12 delayed by 1 month
2024-10
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete


Info from the 2025-01 report (Project first appeared in the 2024-10 report):

Plant Name / State
Westwing / AZ
go live / power
2024-09 / 82MW
status / status verbose
operation / operation
Plant id / generator id
67855 / WESTW
Entity name / entity id
AES Clean Energy / 64904
Changes:
2024-12
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
date: 2024-11 -> 2024-09 accelerated by 2 months