Bellefield Solar and Energy Storage Farm πŸ“β€οΈπŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2021-01
Construction start
Operation start
Estimated start 2025-12
Construction time
Capacity in MWh
1000
πŸ“ This is an estimate
Maximum Power in MW
500
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ 50LW 8me LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.96044827036728+-121.07676030955251
Coordinates
40.96044827036728, -121.07676030955251
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
158 / 64210

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2021-01 report):

Plant Name / State
Bellefield Solar and Energy Storage Farm / CA
go live / power
2025-12 / 500MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
64210 / 50LWB
Entity name / entity id
50LW 8me LLC / 63805
Changes:
2023-01
date: 2024-11 -> 2025-12 delayed by 13 months
2022-02
date: 2023-06 -> 2024-11 delayed by 17 months