Carne Energy Storage, LLC πππ 
Status 
construction 
Country / State / Closest CityπΊπΈ usa / new mexico / 
Dates
    
        
            
                | First heard | 2024-03 | 
            
                | Construction start | 2024-10 | 
            
                | Operation start |  | 
            
                | Estimated start | 2026-03 | 
            
            
                | Construction time |  | 
        
     
 
Capacity in MWh 
    260
     
π  This is an estimate 
Maximum Power in MW130
Manufacturer 
Type / Number of Packs / Cells /  / 
Customer / Owner / Developer / Carne Energy Storage, LLC /  
Use case
Link to google maps satellite viewhttp://maps.google.com/maps?z=19&t=k&q=loc:36.60033402458687+-103.88508735055998 
Coordinates
    36.60033402458687, -103.88508735055998 
    
 π Coords are a guess. Only the state is known
Notes
    
     
     
Project website  
Sources
     
Internal / External id
    1348 / 67230
 U.S. EIA data 
The government data source for this battery is the U.S. Energy Information Administration (EIA)
    https://www.eia.gov/electricity/monthly/
Info from the 
2025-09 report (Project first appeared in the 
2024-03 report):
Plant Name / State
Carne Energy Storage, LLC / NM
go live / power2026-03 / 130MW
status / status verboseconstruction / (V) Under construction, more than 50 percent complete 
Plant id / generator id67230 / CS
Entity name / entity idCarne Energy Storage, LLC / 66107
Changes:
    2025-05
    
        status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete 
     
    
2025-03
    
        date: 2025-11 -> 2026-03 delayed by 
4 months
     
    
2024-10
    
        status: planning -> construction ποΈ
    
        status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete 
    
        date: 2025-08 -> 2025-11 delayed by 
3 months
     
    
2024-07
    
        status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction 
    
        date: 2025-05 -> 2025-08 delayed by 
3 months