TX15 Limousin Oak Storage πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2022-07 |
Construction start |
2023-09 |
Operation start |
|
Estimated start |
2024-08 |
Construction time |
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Key Capture Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.386688295226264+-95.06610767944765
Coordinates
33.386688295226264, -95.06610767944765
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
719 / 65698
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2022-07
report):
Plant Name / State
TX15 Limousin Oak Storage / TX
go live / power
2024-08 / 100MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
65698 / TX15
Entity name / entity id
Key Capture Energy / 63289
Changes:
2024-06
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
2024-04
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2024-03
date: 2024-06 -> 2024-08 delayed by
2 months
2023-09
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
date: 2024-04 -> 2024-06 delayed by
2 months
2023-07
date: 2024-03 -> 2024-04 delayed by
1 month
2023-03
date: 2024-01 -> 2024-03 delayed by
2 months
2023-01
date: 2023-10 -> 2024-01 delayed by
3 months