Franklin Solar Hybrid πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / idaho /
Dates
First heard |
2024-02 |
Construction start |
|
Operation start |
2024-10 |
Estimated start |
2024-06 |
Construction time |
|
Capacity in MWh
200
π This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Franklin Solar Idaho /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:44.16061989624012+-112.7071598353925
Coordinates
44.16061989624012, -112.7071598353925
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1314 / 67190
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-12
report (Project first appeared in the
2024-02
report):
Plant Name / State
Franklin Solar Hybrid / ID
go live / power
2024-10 / 100MW
status / status verbose
operation / operation
Plant id / generator id
67190 / FBESS
Entity name / entity id
Franklin Solar Idaho / 66071
Changes:
2024-12
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2024-11
date: 2024-09 -> 2024-10 delayed by
1 month
2024-08
date: 2024-06 -> 2024-09 delayed by
3 months
2024-05
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete