Ganado Solar πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2024-03 |
Construction start |
|
Operation start |
2024-03 |
Estimated start |
|
Construction time |
|
Capacity in MWh
140
π This is an estimate
Maximum Power in MW
70
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Enel Green Power NA, Inc. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.62803843467857+-95.51290703033499
Coordinates
33.62803843467857, -95.51290703033499
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1368 / 67284
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-03
report):
Plant Name / State
Ganado Solar / TX
go live / power
2024-03 / 70MW
status / status verbose
operation / operation
Plant id / generator id
67284 / GBA
Entity name / entity id
Enel Green Power NA, Inc. / 59380
Changes:
2024-05
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation