Edwards Sanborn S1 πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2021-11 |
Construction start |
|
Operation start |
2022-07 |
Estimated start |
2022-03 |
Construction time |
|
Capacity in MWh
84
π This is an estimate
Maximum Power in MW
42
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Terra-Gen Operating Co-Hybrid /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.94387837493652+-121.3581441949425
Coordinates
40.94387837493652, -121.3581441949425
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
554 / 64929
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-02
report (Project first appeared in the
2021-11
report):
Plant Name / State
Edwards Sanborn S1 / CA
go live / power
2022-07 / 42MW
status / status verbose
operation / operation
Plant id / generator id
64929 / BESS
Entity name / entity id
Terra-Gen Operating Co-Hybrid / 64366
Changes:
2022-09
status: construction -> operation πΎ π πΈ
status_verbose: (TS) Construction complete, but not yet in commercial operation -> operation
2022-08
date: 2022-06 -> 2022-07 delayed by
1 month
2022-07
date: 2022-05 -> 2022-06 delayed by
1 month
2022-06
date: 2022-04 -> 2022-05 delayed by
1 month
2022-05
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2022-03 -> 2022-04 delayed by
1 month
2022-02
mw: 11 -> 42