Stanton Battery Energy Storage πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2023-04 |
Construction start |
2023-06 |
Operation start |
2023-11 |
Estimated start |
2023-08 |
Construction time |
5 months -> 27 MWh/m
|
Capacity in MWh
136
π This is an estimate
Maximum Power in MW
68
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Wellhead Services, Inc /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.96044827036728+-121.07676030955251
Coordinates
40.96044827036728, -121.07676030955251
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
958 / 66423
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2023-04
report):
Plant Name / State
Stanton Battery Energy Storage / CA
go live / power
2023-11 / 68MW
status / status verbose
operation / operation
Plant id / generator id
66423 / BESS1
Entity name / entity id
Wellhead Services, Inc / 20323
Changes:
2024-01
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-12
date: 2023-10 -> 2023-11 delayed by
1 month
2023-11
date: 2023-09 -> 2023-10 delayed by
1 month
2023-10
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2023-08 -> 2023-09 delayed by
1 month
2023-06
status: planning -> construction ποΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete