Myrtle Storage πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-09 |
Construction start |
|
Operation start |
|
Estimated start |
2024-07 |
Construction time |
|
Capacity in MWh
300
π This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Myrtle Storage, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.244054+-95.273438
Coordinates
33.244054, -95.273438
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1055 / 66913
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-09
report):
Plant Name / State
Myrtle Storage / TX
go live / power
2024-07 / 150MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
66913 / MYRST
Entity name / entity id
Myrtle Storage, LLC / 65830
Changes:
2024-06
date: 2024-05 -> 2024-07 delayed by
2 months
2024-04
date: 2024-03 -> 2024-05 delayed by
2 months
2024-03
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2024-02 -> 2024-03 delayed by
1 month
2024-02
date: 2024-01 -> 2024-02 delayed by
1 month
2024-01
date: 2023-12 -> 2024-01 delayed by
1 month
2023-11
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete