GulfStar Power, LLC πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / texas /
Dates
First heard |
2023-09 |
Construction start |
2024-03 |
Operation start |
|
Estimated start |
2024-10 |
Construction time |
|
Capacity in MWh
600
π This is an estimate
Maximum Power in MW
300
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ GulfStar Power, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.319757178933756+-95.37101035188054
Coordinates
33.319757178933756, -95.37101035188054
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1053 / 66871
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2023-09
report):
Plant Name / State
GulfStar Power, LLC / TX
go live / power
2024-10 / 300MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
66871 / BESS
Entity name / entity id
GulfStar Power, LLC / 65805
Changes:
2024-05
date: 2024-06 -> 2024-10 delayed by
4 months
2024-03
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete