Carris Storage I πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2022-08
Construction start 2023-05
Operation start
Estimated start 2024-05
Construction time
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Hecate Grid Carris Storage 1 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.05310153848376+-121.35059853169716
Coordinates
41.05310153848376, -121.35059853169716
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
713 / 65733

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-08 report):

Plant Name / State
Carris Storage I / CA
go live / power
2024-05 / 10MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
65733 / HECAR
Entity name / entity id
Hecate Grid Carris Storage 1 LLC / 64978
Changes:
2024-01
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2024-02 -> 2024-05 delayed by 3 months
2023-11
date: 2023-11 -> 2024-02 delayed by 3 months
2023-08
date: 2023-09 -> 2023-11 delayed by 2 months
2023-05
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2023-02
date: 2023-05 -> 2023-09 delayed by 4 months
2022-11
date: 2023-04 -> 2023-05 delayed by 1 month
2022-09
status_verbose: (L) Regulatory approvals pending. Not under construction -> (T) Regulatory approvals received. Not under construction
date: 2022-12 -> 2023-04 delayed by 4 months