St. Gall Energy Storage I πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2023-03
Construction start 2023-10
Operation start 2024-03
Estimated start 2023-12
Construction time 5 months -> 40 MWh/m
Capacity in MWh
200
πŸ“ This is an estimate
Maximum Power in MW
100
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ St. Gall Energy Storage I /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.322390103486484+-95.45465780673999
Coordinates
33.322390103486484, -95.45465780673999
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
992 / 66336

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-07 report (Project first appeared in the 2023-03 report):

Plant Name / State
St. Gall Energy Storage I / TX
go live / power
2024-03 / 100MW
status / status verbose
operation / operation
Plant id / generator id
66336 / SGES1
Entity name / entity id
St. Gall Energy Storage I / 65426
Changes:
2024-05
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> operation
date: 2024-04 -> 2024-03 accelerated by 1 month
2024-04
date: 2024-03 -> 2024-04 delayed by 1 month
2024-03
date: 2024-02 -> 2024-03 delayed by 1 month
2024-02
date: 2024-01 -> 2024-02 delayed by 1 month
2023-10
status: planning -> construction πŸ—οΈ
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (U) Under construction, less than or equal to 50 percent complete
2023-09
date: 2023-12 -> 2024-01 delayed by 1 month