Serrano πππ
Status
construction
Country / State / Closest City
πΊπΈ usa / arizona /
Dates
First heard |
2024-05 |
Construction start |
|
Operation start |
|
Estimated start |
2025-06 |
Construction time |
|
Capacity in MWh
426
π This is an estimate
Maximum Power in MW
213
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Serrano Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.63537829690874+-109.99928433894475
Coordinates
36.63537829690874, -109.99928433894475
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1327 / 67503
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-07
report (Project first appeared in the
2024-05
report):
Plant Name / State
Serrano / AZ
go live / power
2025-06 / 213MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
67503 / GEN02
Entity name / entity id
Serrano Solar, LLC / 66226