AES Waiawa Phase 2 Solar πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / hawaii /
Dates
First heard 2022-12
Construction start 2023-09
Operation start
Estimated start 2024-11
Construction time
Capacity in MWh
60
πŸ“ This is an estimate
Maximum Power in MW
30
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ AES Distributed Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:19.406354683428763+-155.3642375459177
Coordinates
19.406354683428763, -155.3642375459177
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
857 / 66066

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-12 report):

Plant Name / State
AES Waiawa Phase 2 Solar / HI
go live / power
2024-11 / 30MW
status / status verbose
construction / (V) Under construction, more than 50 percent complete
Plant id / generator id
66066 / WAIBA
Entity name / entity id
AES Distributed Energy / 61012
Changes:
2023-12
date: 2024-10 -> 2024-11 delayed by 1 month
2023-11
date: 2023-12 -> 2024-10 delayed by 10 months
2023-09
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (V) Under construction, more than 50 percent complete