Upton BESS 2 πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2023-03
Construction start
Operation start
Estimated start 2024-12
Construction time
Capacity in MWh
300
πŸ“ This is an estimate
Maximum Power in MW
150
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Consolidated Edison Development Inc. /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.65154984477027+-95.54526771010998
Coordinates
33.65154984477027, -95.54526771010998
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
988 / 66303

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-03 report):

Plant Name / State
Upton BESS 2 / TX
go live / power
2024-12 / 150MW
status / status verbose
planning / (P) Planned for installation, but regulatory approvals not initiated
Plant id / generator id
66303 / UPBS2
Entity name / entity id
Consolidated Edison Development Inc. / 56769
Changes:
2024-02
date: 2024-05 -> 2024-12 delayed by 7 months