Dodge Flat πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / nevada /
Dates
First heard 2021-06
Construction start 2021-08
Operation start 2022-03
Estimated start
Construction time 7 months -> 14 MWh/m
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Dodge Flat Solar, LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.543396+-114.96600600000001
Coordinates
41.543396, -114.96600600000001
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
230 / 63913

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2021-06 report):

Plant Name / State
Dodge Flat / NV
go live / power
2022-03 / 50MW
status / status verbose
operation / operation
Plant id / generator id
63913 / DODGB
Entity name / entity id
Dodge Flat Solar, LLC / 63578
Changes:
2022-05
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-03
date: 2022-02 -> 2022-03 delayed by 1 month
2022-02
date: 2021-12 -> 2022-02 delayed by 2 months
2021-08
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete