Dodge Flat πππ 
Status 
operation 
Country / State / Closest CityπΊπΈ usa / nevada / 
Dates
    
        
            
                | First heard | 2021-06 | 
            
                | Construction start | 2021-08 | 
            
                | Operation start | 2022-03 | 
            
                | Estimated start | 2021-12 | 
            
            
                | Construction time | 7 months -> 14 MWh/m | 
        
     
 
Capacity in MWh 
    100
     
π  This is an estimate 
Maximum Power in MW50
Manufacturer 
Type / Number of Packs / Cells /  / 
Customer / Owner / Developer / Dodge Flat Solar, LLC /  
Use case
Link to google maps satellite viewhttp://maps.google.com/maps?z=19&t=k&q=loc:41.543396+-114.96600600000001 
Coordinates
    41.543396, -114.96600600000001 
    
 π Coords are a guess. Only the state is known
Notes
    
     
     
Project website  
Sources
     
Internal / External id
    230 / 63913
 U.S. EIA data 
The government data source for this battery is the U.S. Energy Information Administration (EIA)
    https://www.eia.gov/electricity/monthly/
Info from the 
2023-02 report (Project first appeared in the 
2021-06 report):
Plant Name / State
Dodge Flat / NV
go live / power2022-03 / 50MW
status / status verboseoperation / operation 
Plant id / generator id63913 / DODGB
Entity name / entity idDodge Flat Solar, LLC / 63578
Changes:
    2022-05
    
        status: construction -> operation πΎ π πΈ
    
        status_verbose: (V) Under construction, more than 50 percent complete -> operation 
     
    
2022-03
    
        date: 2022-02 -> 2022-03 delayed by 
1 month
     
    
2022-02
    
        date: 2021-12 -> 2022-02 delayed by 
2 months
     
    
2021-08
    
        status: planning -> construction ποΈ
    
        status_verbose: (L) Regulatory approvals pending. Not under construction -> (V) Under construction, more than 50 percent complete