Clairemont Energy Storage πŸ“πŸ“ŠπŸ“

Status
construction
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california /
Dates
First heard 2023-02
Construction start 2023-04
Operation start
Estimated start 2024-03
Construction time
Capacity in MWh
20
πŸ“ This is an estimate
Maximum Power in MW
10
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ San Diego Gas & Electric Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:40.952677+-121.300049
Coordinates
40.952677, -121.300049
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
935 / 66266

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2023-02 report):

Plant Name / State
Clairemont Energy Storage / CA
go live / power
2024-03 / 10MW
status / status verbose
construction / (TS) Construction complete, but not yet in commercial operation
Plant id / generator id
66266 / 1
Entity name / entity id
San Diego Gas & Electric Co / 16609
Changes:
2024-01
date: 2023-12 -> 2024-03 delayed by 3 months
2023-11
status_verbose: (V) Under construction, more than 50 percent complete -> (TS) Construction complete, but not yet in commercial operation
date: 2023-09 -> 2023-12 delayed by 3 months
2023-10
date: 2023-08 -> 2023-09 delayed by 1 month
2023-07
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-04
status: planning -> construction πŸ—οΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete