AGATE BESS πŸ“πŸ“ŠπŸ“

Status
planning
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / washington /
Dates
First heard 2025-01
Construction start
Operation start
Estimated start 2027-12
Construction time
Capacity in MWh
340
πŸ“ This is an estimate
Maximum Power in MW
170
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ BrightNight Power /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:48.226745+-118.030897
Coordinates
48.226745, -118.030897
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
1675 / 68366

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2025-01 report (Project first appeared in the 2025-01 report):

Plant Name / State
AGATE BESS / WA
go live / power
2027-12 / 170MW
status / status verbose
planning / (L) Regulatory approvals pending. Not under construction
Plant id / generator id
68366 / AGAT
Entity name / entity id
BrightNight Power / 66731
Changes: