Coso Battery Storage πŸ“πŸ“ŠπŸ‘€

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / california / Coso Junction, Little Lake
Dates
First heard 2020-10
Construction start 2021-05
Operation start 2022-04
Estimated start
Construction time 11 months -> 21 MWh/m
Capacity in MWh
240
Maximum Power in MW
60
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Arevon Asset Management / Arevon
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.056513+-117.858611
Coordinates
36.056513, -117.858611
πŸ“ Coords not known
Notes
took the location from arevon website, but on google maps satellite seems like an unlikely location, this project is most likely tesla given that arevon has signed a large deal with tesla
Project website
https://arevonenergy.com/location/coso/
Sources
https://arevonenergy.com/arevon-signs-agreement-for-2-gw-6-gwh-of-tesla-megapack-systems/
Internal / External id
117 / 63943

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2023-02 report (Project first appeared in the 2020-10 report):

Plant Name / State
Coso Battery Storage / CA
go live / power
2022-04 / 60MW
status / status verbose
operation / operation
Plant id / generator id
63943 / 61730
Entity name / entity id
Arevon Asset Management / 64172
Changes:
2022-06
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-05
date: 2022-03 -> 2022-04 delayed by 1 month
2022-04
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2022-02 -> 2022-03 delayed by 1 month
2022-03
date: 2022-01 -> 2022-02 delayed by 1 month
2022-02
date: 2021-12 -> 2022-01 delayed by 1 month
2021-12
date: 2021-11 -> 2021-12 delayed by 1 month
2021-10
date: 2021-10 -> 2021-11 delayed by 1 month
2021-08
date: 2021-08 -> 2021-10 delayed by 2 months
2021-05
status: planning -> construction πŸ—οΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2021-04
entity id: 63611 -> 64172
entity name: Coso Battery Storage LLC -> Arevon Asset Management
2021-03
date: 2021-06 -> 2021-08 delayed by 2 months