Coso Battery Storage πππ€
Status
operation
Country / State / Closest City
πΊπΈ usa / california / Coso Junction, Little Lake
Dates
First heard |
2020-10 |
Construction start |
2021-05 |
Operation start |
2022-04 |
Estimated start |
|
Construction time |
11 months -> 21 MWh/m
|
Capacity in MWh
240
Maximum Power in MW
60
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Arevon Asset Management / Arevon
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:36.056513+-117.858611
Coordinates
36.056513, -117.858611
π Coords not known
Notes
took the location from arevon website, but on google maps satellite seems like an unlikely location, this project is most likely tesla given that arevon has signed a large deal with tesla
Project website
https://arevonenergy.com/location/coso/
Sources
https://arevonenergy.com/arevon-signs-agreement-for-2-gw-6-gwh-of-tesla-megapack-systems/
Internal / External id
117 / 63943
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2023-02
report (Project first appeared in the
2020-10
report):
Plant Name / State
Coso Battery Storage / CA
go live / power
2022-04 / 60MW
status / status verbose
operation / operation
Plant id / generator id
63943 / 61730
Entity name / entity id
Arevon Asset Management / 64172
Changes:
2022-06
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2022-05
date: 2022-03 -> 2022-04 delayed by
1 month
2022-04
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2022-02 -> 2022-03 delayed by
1 month
2022-03
date: 2022-01 -> 2022-02 delayed by
1 month
2022-02
date: 2021-12 -> 2022-01 delayed by
1 month
2021-12
date: 2021-11 -> 2021-12 delayed by
1 month
2021-10
date: 2021-10 -> 2021-11 delayed by
1 month
2021-08
date: 2021-08 -> 2021-10 delayed by
2 months
2021-05
status: planning -> construction ποΈ
status_verbose: (L) Regulatory approvals pending. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2021-04
entity id: 63611 -> 64172
entity name: Coso Battery Storage LLC -> Arevon Asset Management
2021-03
date: 2021-06 -> 2021-08 delayed by
2 months