Daggett 2 πππ
Status
operation
Country / State / Closest City
πΊπΈ usa / california /
Dates
First heard |
2021-09 |
Construction start |
2023-01 |
Operation start |
2023-12 |
Estimated start |
2023-06 |
Construction time |
11 months -> 23 MWh/m
|
Capacity in MWh
262
π This is an estimate
Maximum Power in MW
131
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Daggett Solar Power 2 LLC /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:41.34434765645874+-121.46110215912815
Coordinates
41.34434765645874, -121.46110215912815
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
167 / 64851
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-02
report (Project first appeared in the
2021-09
report):
Plant Name / State
Daggett 2 / CA
go live / power
2023-12 / 131MW
status / status verbose
operation / operation
Plant id / generator id
64851 / DAGGB
Entity name / entity id
Daggett Solar Power 2 LLC / 64364
Changes:
2024-02
status: construction -> operation πΎ π πΈ
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-11
date: 2023-11 -> 2023-12 delayed by
1 month
2023-10
date: 2023-10 -> 2023-11 delayed by
1 month
2023-08
date: 2023-09 -> 2023-10 delayed by
1 month
2023-07
date: 2023-11 -> 2023-09 accelerated by
2 months
2023-04
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
2023-01
status: planning -> construction ποΈ
status_verbose: (T) Regulatory approvals received. Not under construction -> (U) Under construction, less than or equal to 50 percent complete
2022-08
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
date: 2023-06 -> 2023-11 delayed by
5 months