TX21 River Valley Storage 2 πŸ“πŸ“ŠπŸ“

Status
operation
Country / State / Closest City
πŸ‡ΊπŸ‡Έ usa / texas /
Dates
First heard 2022-07
Construction start
Operation start 2023-07
Estimated start
Construction time
Capacity in MWh
100
πŸ“ This is an estimate
Maximum Power in MW
50
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Key Capture Energy /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:33.604054+-95.273438
Coordinates
33.604054, -95.273438
πŸ“ Coords are a guess. Only the state is known
Notes

Project website
Sources
Internal / External id
725 / 65700

U.S. EIA data

The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the 2024-02 report (Project first appeared in the 2022-07 report):

Plant Name / State
TX21 River Valley Storage 2 / TX
go live / power
2023-07 / 50MW
status / status verbose
operation / operation
Plant id / generator id
65700 / TX21
Entity name / entity id
Key Capture Energy / 63289
Changes:
2023-09
status: construction -> operation 🍾 πŸŽ‰ 🍸
status_verbose: (V) Under construction, more than 50 percent complete -> operation
2023-07
date: 2023-05 -> 2023-07 delayed by 2 months
2023-05
date: 2023-03 -> 2023-05 delayed by 2 months
2022-12
status_verbose: (U) Under construction, less than or equal to 50 percent complete -> (V) Under construction, more than 50 percent complete
date: 2023-01 -> 2023-03 delayed by 2 months
2022-11
date: 2022-12 -> 2023-01 delayed by 1 month