Dover Solar πππ
Status
cancelled
Country / State / Closest City
πΊπΈ usa / florida /
Dates
First heard |
2023-08 |
Construction start |
|
Operation start |
|
Estimated start |
2024-09 |
Month disappeared |
2024-02 |
Construction time |
|
Capacity in MWh
30
π This is an estimate
Maximum Power in MW
15
Manufacturer
Type / Number of Packs / Cells
/ /
Customer / Owner / Developer
/ Tampa Electric Co /
Use case
Link to google maps satellite view
http://maps.google.com/maps?z=19&t=k&q=loc:30.291761494737585+-82.095607144945
Coordinates
30.291761494737585, -82.095607144945
π Coords are a guess. Only the state is known
Notes
Project website
Sources
Internal / External id
1044 / 66129
U.S. EIA data
The government data source for this battery is the U.S. Energy Information Administration (EIA)
https://www.eia.gov/electricity/monthly/
Info from the
2024-01
report (Project first appeared in the
2023-08
report):
Plant Name / State
Dover Solar / FL
go live / power
2024-09 / 15MW
status / status verbose
planning / (T) Regulatory approvals received. Not under construction
Plant id / generator id
66129 / BESS1
Entity name / entity id
Tampa Electric Co / 18454
Changes:
2024-01
status_verbose: (P) Planned for installation, but regulatory approvals not initiated -> (T) Regulatory approvals received. Not under construction
2024-02
This project disappeared in the
2024-02
report.
That's why the status was set to
cancelled